Step 4
Step 5
26
Level the pedestal plumb within ±0.5° using the leveling nuts provided.
Secure pedestal with washer and nuts as shown in Figure 17.
Installation Procedures
Figure 17 (Manual Mount)
302677
Pedestal Assembly
Foundation
Anchor Bolts,
Nuts and Washers
(Part of Andrew 302689)
Level Pedestal
Plumb Within ±0.5°
Optional: Fill Cavity With
Non-Shrinking Grout
Split PVC Drain Required
if Cavity is Grouted
Hex Nut
(9999-182)
Flat Washer
(9997-229)
Reference Drawing 240299
Figure 17A (Motorized Mount)
Anchor Bolts,
Nuts and Washers
(Part of Andrew 302689)
Foundation
303158
Pedestal Assembly
Optional: Fill Cavity With
Non-Shrinking Grout
Level Pedestal
Plumb Within ±0.5°
Split PVC Drain Required
if Cavity is Grouted
Reference Drawing 240349
208366
Az/El Jack
Assembly
Note: Jacks are not
installed until after the
pedestal is securely
attached to the foundation.